| Inspection Tasks Prior to Bolting | Sections |
|---|---|
| Manufacturer’s certifications available for fastener materials | 2.9 |
| Fasteners marked in accordance with ASTM requirements | Figure C-2.1, (also see ASTM standards) |
| Correct fasteners selected for the joint detail (grade, type, bolt length if threads are to be excluded from shear plane) | 2.7 |
| Correct bolting procedure selected for joint detail | 4, 8 |
| Connecting elements, including the appropriate faying surface condition and hole preparation, if specified, meet applicable requirements | 3.2, 3.4, 4, 9.3 |
| Pre-installation verification testing by installation person- nel observed and documented for fastener assemblies and methods used | 7, 8.2, 9.2 |
| Protected storage provided for bolts, nuts, washers, and other fastener components | 2.10 |
2. PDF page 637
| Inspection Tasks During Bolting | Sections |
|---|---|
| Fastener assemblies placed in all holes and washers (if required) are positioned as required | 7.1, 8.1, 8.2 |
| Joint brought to the snug-tight condition prior to the pretensioning operation | 8.1, 8.2, 9.1 |
| Fastener component not turned by the wrench prevented from rotating | 8.2 |
| Fasteners are pretensioned in accordance with a method approved by RCSC and progressing systematically from most rigid point toward free edges | 8.1, 8.2 |