Table N5.6-2: Inspection Tasks During Bolting
PDF page 260 · AISC 360-22
| Inspection Tasks During Bolting | QC | QA |
|---|---|---|
| Fastener assemblies placed in all holes, and washers and nuts are positioned as required | O | O |
| Joint brought to the snug-tight condition prior to the pretensioning operation | O | O |
| Fastener component not turned by the wrench prevented from rotating | O | O |
| Fasteners are pretensioned in accordance with the RCSC Specification, progressing systematically from the most rigid point toward the free edges | O | O |

Figure description:
TABLE N5.6-3 Inspection Tasks After Bolting
Inspection Tasks After Bolting
| Inspection Tasks After Bolting | QC | QA |
|---|---|---|
| Document acceptance or rejection of bolted connections | P | P |