TablesN Quality control and quality assurance
Table N5.4-1: Inspection Tasks Prior to Welding
PDF page 255 · AISC 360-22
| Inspection Tasks Prior to Welding | QC | QA |
|---|---|---|
| Welder qualification records and continuity records | P | O |
| WPS available | P | P |
| Manufacturer certifications for welding consumables available | P | P |
| Material identification (type/grade) | O | O |
| Welder identification system • Fabricator or erector, as applicable, shall maintain a system by which a welder who has welded a joint or member can be identified. • Die stamping of members subjected to fatigue shall be prohibited unless approved by the engineer of record. | O | O |
| Fit-up of groove welds (including joint geometry) • Joint preparations • Dimensions (alignment, root opening, root face, bevel) • Cleanliness (condition of steel surfaces) • Tacking (tack weld quality and location) • Backing type and fit (if applicable) | O | O |
| Fit-up of CJP groove welds of HSS T-, Y-, and K-connections with-out backing (including joint geometry) • Joint preparations • Dimensions (alignment, root opening, root face, bevel) • Cleanliness (condition of steel surfaces) • Tacking (tack weld quality and location) | P | O |
| Configuration and finish of access holes | O | O |
| Fit-up of fillet welds • Dimensions (alignment, gaps at root) • Cleanliness (condition of steel surfaces) • Tacking (tack weld quality and location) | O | O |
| Check welding equipment | O | − |